Do not move the evidence before you record it.
Compare package count with the transport document, photograph the shipment on the vehicle and at the receiving point, capture every label and note visible exceptions before signing. If there is serious damage or an unsafe condition, stop and follow the written carrier, insurer and supplier process.
Delivery inspection sequence
- Prepare: have the purchase order, packing list, approved model and receiving contact ready.
- Count: reconcile pallets, crates, cartons and loose items before unloading is complete.
- Photograph: capture overview, every side, labels, seals, corners, straps and visible impact or moisture.
- Record exceptions: write observable facts, not guesses about cause.
- Segregate: keep suspect packages protected and separate.
- Unpack methodically: preserve labels and internal protection while checking parts.
- Report: send one evidence set linked to package and part numbers.
What to check by shipment layer
| Layer | Checks | Evidence |
|---|---|---|
| Transport unit | Package count, orientation, movement, water or impact signs | Wide photos before unloading |
| Crate or carton | Label, seal, puncture, crush, corner and strap condition | All sides plus label close-up |
| Internal protection | Foam, blocking, wrap, moisture barrier and movement | Photos before components are removed |
| Major components | Bed/slate, cabinet, rails, legs, frame and tops | Part ID and affected surface |
| Hardware and accessories | Fasteners, feet, pockets, balls, cues, cloth and manuals | Count against packing list |
Damage notes should be factual
Write “right-front crate corner crushed approximately 60 mm; rail carton beneath shows torn wrap” rather than “factory packed it badly.” Record time, location, package ID and who was present. Do not discard packaging until the evidence and disposition are agreed.
Parts quarantine and release
Mark suspect parts so an installer cannot accidentally use them. Separate cosmetic issues from structural, playing or safety issues, but do not decide acceptance rules during unloading. Use the purchase specification, contract, insurance and written claim process.
Send a complete evidence packet
- Purchase order and shipment reference
- Delivery date, location and receiving contact
- Package count received versus expected
- Transport and package photos in sequence
- Package and part identifiers
- Measured damage and affected quantity
- Requested next action, without destroying evidence
Contract and carrier procedures control claims.
This checklist is an original receiving workflow for evidence preservation. It does not replace the bill of lading, Incoterm, insurance policy, carrier procedure, purchase contract, local law or safety instructions. Confirm deadlines and required notice with the responsible parties.
Reviewed November 11, 2026. Commercial responsibility, claim eligibility and remedy are order-specific.